Ulaanbaatar, May 13, 2026 /MONTSAME/. According to the Ministry of Road and Transport, construction of the Bagakhangai-Khushigt Valley-Emeelt Railway Project is progressing rapidly and on schedule.
Within the project, work is underway on the railway’s substructure and superstructure works, bridge facilities, and procurement of materials and equipment. Contractors are also building site access points and temporary roads, as well as carrying out soil stripping, excavation, and embankment works.
According to engineers and technical staff of the Mongolian Railway state-owned shareholding company, excavation side slopes are being designed with a 1:1.5 ratio, an 8-meter height, and 4-meter berms to avoid disrupting vehicle traffic. Concrete sleepers are also being installed along the railway alignment in accordance with detailed engineering designs.
Moreover, Ulaanbaatar Railway has supplied 75 wagonloads, or 3,375 cubic meters, of gravel, of which 691 cubic meters have already been unloaded. At the construction site, plans are in place to crush 4,066 cubic meters of stone, while 540 cubic meters of ballast have already been produced and prepared.
Girder bridge construction is also progressing in stages, including backfilling of bridge supports and installation of reinforcement and formwork for intermediate support beams.
As part of the project, Ulaanbaatar BUK LLC is expected to supply 128,610 concrete sleepers, of which 90,064 have been delivered so far.